2003 Activities
 
October
  • Official Opening Ceremony for Phase 1 (Segment 1) by the Most Hon P J Patterson, Prime Minister of Jamaica on October 9 at the Vineyards Toll Plaza. Prime Minister P J Patterson also paid his first toll.
September
  • Toll charges at the Vineyards Toll Plaza commence on September 25
  • Non-revenue operations commence at the Vineyards Toll Plaza, Old Harbour on September 22.
  • Dr Compton Bourne, President of the Caribbean Development Bank and other senior staff tour the Highway 2000 Project.
  • Commissioning and opening of the dualized Old Harbour Bypass and the Vineyards Toll Plaza at Bushy Park.
  • Official Media Tour of the Old Harbour Bypass.

 

August
  • Visit of the Director General of the Malaysian Highway Authority, Dato George George accompanied by other Malaysian engineers.
  • Toll Regulator and Board Members of the Toll Authority appointed by Minister of Transport & Works.
July
  • Completion of civil works for the OHB dualization
June
  • NROCC meets with the Overseas Private Investment Corporation (OPIC) and awaiting the Standard and Poor's Shadow Rating.
  • EIA for Causeway in progress
  • Earthworks between 7-KM 21, that is, Port Henderson Road to Bushy Park is in progress
May
  • JPS relocation of electrical lines at Bushy Park
  • Toll Manager, Mr. Colin Murray appointed by Trans Jamaican Highway Limited.
  • Update of traffic study with additional traffic counts for Ferry, OHB and Portmore Causeway
  • Executive officials of Bouygues visit the  Project site.
January
  • Parliamentary guarantee for US investors in the project
  • Trans Jamaican Highway Limited(TJH) meets with NEPA re Portmore Causeway.

 

 

 

 

 

 

 

 