| January |
- Parliamentary guarantee for US investors in the project
- Trans Jamaican Highway Limited(TJH) meets with NEPA re Portmore Causeway.
|
| May |
- JPS relocation of electrical lines at Bushy Park
- Toll Manager, Mr. Colin Murray appointed by Trans Jamaican Highway Limited.
- Update of traffic study with additional traffic counts for Ferry, OHB and Portmore Causeway
- Executive officials of Bouygues visit the Project site.
|
| June |
- NROCC meets with the Overseas Private Investment Corporation (OPIC) and awaiting the Standard and Poor's Shadow Rating.
- EIA for Causeway in progress
- Earthworks between 7-KM 21, that is, Port Henderson Road to Bushy Park is in progress
|
| July |
- Completion of civil works for the OHB dualization
|
| August |
- Visit of the Director General of the Malaysian Highway Authority, Dato George George accompanied by other Malaysian engineers.
- Toll Regulator and Board Members of the Toll Authority appointed by Minister of Transport & Works.
|
| September |
- Toll charges at the Vineyards Toll Plaza commence on September 25
- Non-revenue operations commence at the Vineyards Toll Plaza, Old Harbour on September 22.
- Dr Compton Bourne, President of the Caribbean Development Bank and other senior staff tour the Highway 2000 Project.
- Commissioning and opening of the dualized Old Harbour Bypass and the Vineyards Toll Plaza at Bushy Park.
- Official Media Tour of the Old Harbour Bypass.
|
| October |
- Official Opening Ceremony for Phase 1 (Segment 1) by the Most Hon P J Patterson, Prime Minister of Jamaica on October 9 at the Vineyards Toll Plaza. Prime Minister P J Patterson also paid his first toll.
|