Project Highway 200 Schedule

The Highway 2000 Project is being implemented in a phased approach according the following Project Schedule:

  • Phase 1       Kingston – Mandeville
  • Phase 1a     Old Harbour Dualization - (km 21-33) Sept. 25, 2003
                            Kingston to Bushy Park -  (km 0-21) Dec. 15, 2005
    Portmore Causeway June 2006
  • Phase 1b     Sandy Bay to Williamsfield - (km 33-71)
  • Phase 2a     Old Harbour - Ocho Rios
  • Phase 2b      Mandeville - Montego Bay

 To learn more about individual activities taking place over the years, please view the following pages: